Which method is primarily used in project management to identify the longest sequence of dependent tasks that determines the minimum project duration?

A) Monte Carlo Simulation

B) Linear Programming

C) Critical Path Method (CPM)

D) Program Evaluation and Review Technique (PERT)

Avatar
Discard
Best Answer

C) Critical Path Method (CPM)